Assessment Year | 1998 |
---|---|
Principal Product | liquid egg products |
NAICS |
n/a
|
SIC | 2015: Poultry Slaughtering and Processing |
Sales Range | $50 M to 100M |
# of Employees | 180 |
Plant Area |
87,000
ft2
|
Annual Production | 150,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $187,225 | 8,070,340 |
kWh
|
$0.023 |
Electricity Demand | $94,662 | 17,328 |
kW-mo/yr
|
$5.46 |
Natural Gas | $196,724 | 46,803 |
MMBtu
|
$4.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $511,613 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $238,253 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $8,258 | $1,910 |
$(-260.0)
(-11,430)
kWh
|
- | - |
$8,518
-
MMBtu
|
- | - | - | - | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,851 | $500 | - | - | - |
$2,941
-
MMBtu
|
- | - | $(-90.0) | - | |
03 | 2.4133: Use most efficient type of electric motors | $298 | $446 |
$205
8,792
kWh
|
$93
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 2.1213: Direct warmest air to combustion intake | $1,222 | $566 | - | - | - |
$1,222
-
MMBtu
|
- | - | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,390 | $150 |
$974
42,204
kWh
|
$416
-
kW-mo/yr
|
- | - | - | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,346 | $69 |
$1,034
44,842
kWh
|
$312
-
kW-mo/yr
|
- | - | - | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,283 | $3,501 |
$901
38,980
kWh
|
$382
-
kW-mo/yr
|
- | - | - | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $786 | $1,116 |
$554
24,033
kWh
|
$232
-
kW-mo/yr
|
- | - | - | - | - | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,158 | $25 |
$773
33,411
kWh
|
$385
-
kW-mo/yr
|
- | - | - | - | - | - | |
10 | 2.7135: Install occupancy sensors | $1,026 | $1,396 |
$1,026
44,549
kWh
|
- | - | - | - | - | - | - | |
11 | 3.5311: Recover and reuse waste material | $1,040 | $400 | - | - | - | - | - |
$1,040
-
lb
|
- | - | |
12 | 3.4156: Use flow control valves on equipment to optimize water use | $2,196 | $96 | - | - | - | - |
$2,196
-
Tgal
|
- | - | - | |
13 | 4.446: Automate finishing process | $268,205 | $395,000 |
$(-7,207.0)
(-312,134)
kWh
|
$(-4,588.0)
-
kW-mo/yr
|
- | - | - | - | $280,000 | - | |
14 | 4.446: Automate finishing process | $190,000 | $100,000 | - | - | $(-10,000.0) | - | - | - | $200,000 | - | |
15 | 2.8113: Purchase gas directly from a contract gas supplier | $30,554 | $4,200 | - | - | - | - | - | - | - | $30,554 | |
TOTAL RECOMMENDED | $511,613 | $509,375 |
$(-2,000.0)
(-86,753)
kWh
|
$(-2,768.0)
-
kW-mo/yr
|
$(-10,000.0) |
$12,681
-
MMBtu
|
$2,196
-
Tgal
|
$1,040
-
lb
|
$479,910 | $30,554 | ||
TOTAL IMPLEMENTED | $238,253 | $108,857 |
$1,328
57,445
kWh
|
$544
-
kW-mo/yr
|
$(-10,000.0) |
$12,681
-
MMBtu
|
$2,196
-
Tgal
|
$1,040
-
lb
|
$199,910 | $30,554 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs