Assessment Year | 1998 |
---|---|
Principal Product | fluid film bearings |
NAICS |
n/a
|
SIC | 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 440 |
Plant Area |
176,000
ft2
|
Annual Production | 13,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $382,082 | 15,311,548 |
kWh
|
$0.025 |
Electricity Demand | $95,746 | 35,556 |
kW-mo/yr
|
$2.69 |
Natural Gas | $92,516 | 23,175 |
MMBtu
|
$3.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $91,742 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $53,992 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.1191: Change procedures / equipment / operating conditions | $40,823 | $2,000 | - | - | - |
$33,623
-
gal
|
$7,200
-
gal
|
- | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $13,413 | $621 |
$11,165
463,365
kWh
|
$2,248
-
kW-mo/yr
|
- | - | - | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,065 | $23,277 |
$7,796
323,564
kWh
|
$1,269
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 2.4314: Use synthetic lubricant | $10,496 | - |
$6,374
264,654
kWh
|
$1,137
-
kW-mo/yr
|
- | - |
$2,715
-
gal
|
$270 | - | - | |
05 | 2.8113: Purchase gas directly from a contract gas supplier | $6,437 | $2,950 | - | - | - | - | - | - | $6,437 | - | |
06 | 3.6192: Use a less expensive method of waste removal | $6,030 | $550 | - | - | - | - | - | - | - | $6,030 | |
07 | 2.7135: Install occupancy sensors | $2,597 | $1,530 |
$2,597
108,148
kWh
|
- | - | - | - | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,783 | $2,626 |
$1,550
64,185
kWh
|
$233
-
kW-mo/yr
|
- | - | - | - | - | - | |
09 | 2.1233: Analyze flue gas for proper air/fuel ratio | $890 | $2,000 | - | - |
$890
-
MMBtu
|
- | - | - | - | - | |
10 | 2.1213: Direct warmest air to combustion intake | $208 | $733 | - | - |
$208
-
MMBtu
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $91,742 | $36,287 |
$29,482
1,223,916
kWh
|
$4,887
-
kW-mo/yr
|
$1,098
-
MMBtu
|
$33,623
-
gal
|
$9,915
-
gal
|
$270 | $6,437 | $6,030 | ||
TOTAL IMPLEMENTED | $53,992 | $6,626 |
$7,924
328,839
kWh
|
$1,370
-
kW-mo/yr
|
$890
-
MMBtu
|
$33,623
-
gal
|
$9,915
-
gal
|
$270 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs