ITAC Assessment: IA0203
ITAC logo
ITAC Assessment: IA0203
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product fluid film bearings
NAICS
n/a
SIC 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 440
Plant Area 176,000
ft2
Annual Production 13,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $382,082 15,311,548
kWh
Electricity Demand $95,746 35,556
kW-mo/yr
Natural Gas $92,516 23,175
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $91,742 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $53,992

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 3.1191: Change procedures / equipment / operating conditions $40,823 $2,000 - - - $33,623
-
gal
$7,200
-
gal
- - -
02 2.4221: Install compressor air intakes in coolest locations $13,413 $621 $11,165
463,365
kWh
$2,248
-
kW-mo/yr
- - - - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $9,065 $23,277 $7,796
323,564
kWh
$1,269
-
kW-mo/yr
- - - - - -
04 2.4314: Use synthetic lubricant $10,496 - $6,374
264,654
kWh
$1,137
-
kW-mo/yr
- - $2,715
-
gal
$270 - -
05 2.8113: Purchase gas directly from a contract gas supplier $6,437 $2,950 - - - - - - $6,437 -
06 3.6192: Use a less expensive method of waste removal $6,030 $550 - - - - - - - $6,030
07 2.7135: Install occupancy sensors $2,597 $1,530 $2,597
108,148
kWh
- - - - - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $1,783 $2,626 $1,550
64,185
kWh
$233
-
kW-mo/yr
- - - - - -
09 2.1233: Analyze flue gas for proper air/fuel ratio $890 $2,000 - - $890
-
MMBtu
- - - - -
10 2.1213: Direct warmest air to combustion intake $208 $733 - - $208
-
MMBtu
- - - - -
TOTAL RECOMMENDED $91,742 $36,287 $29,482
1,223,916
kWh
$4,887
-
kW-mo/yr
$1,098
-
MMBtu
$33,623
-
gal
$9,915
-
gal
$270 $6,437 $6,030
TOTAL IMPLEMENTED $53,992 $6,626 $7,924
328,839
kWh
$1,370
-
kW-mo/yr
$890
-
MMBtu
$33,623
-
gal
$9,915
-
gal
$270 - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs