Assessment Year | 1993 |
---|---|
Principal Product | metal job shop |
NAICS |
n/a
|
SIC | 2869: Industrial Organic Chemicals, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 30 |
Plant Area |
45,000
ft2
|
Annual Production | 475,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $113,355 | 2,359,320 |
kWh
|
$0.048 |
Natural Gas | $16,369 | 3,716 |
MMBtu
|
$4.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,512 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,512 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3522: Increase electrical conductor size to reduce distribution losses | $2,303 | $6,000 |
$2,303
-
kWh
|
- | |
02 | 2.3191: Use demand controller or load shedder | $4,300 | $1,000 |
$4,300
-
kWh
|
- | |
03 | 2.3191: Use demand controller or load shedder | $1,563 | $500 |
$1,563
-
kWh
|
- | |
04 | 2.7132: Install timers on light switches in little used areas | $2,346 | $1,500 |
$2,733
70,047
kWh
|
$(-387.0)
-
MMBtu
|
|
TOTAL RECOMMENDED | $10,512 | $9,000 |
$10,899
70,047
kWh
|
$(-387.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $10,512 | $9,000 |
$10,899
70,047
kWh
|
$(-387.0)
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs