ITAC Assessment: IA0184
ITAC logo
ITAC Assessment: IA0184
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product leather
NAICS
n/a
SIC 3111: Leather Tanning and Finishing
Sales Range $1
M
to 5
M
# of Employees 280
Plant Area 115,000
ft2
Annual Production 300,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $152,602 3,346,424
kWh
Electricity Demand $19,034 9,660
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $123,343 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $107,054

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings By-product Production Savings
01 2.8113: Purchase gas directly from a contract gas supplier $71,892 $4,200 - - - - $71,892 - -
02 2.4239: Eliminate or reduce compressed air usage $20,390 $7,000 $15,523
337,632
kWh
$4,867
-
kW-mo/yr
- - - - -
03 3.7198: Reduce / eliminate use of disposable product $11,251 $1,800 - - $303
-
lb
$2,163 - $8,785 -
04 3.5315: Lease / purchase baler; sell cardboard to recycler $8,647 $8,400 - - $6,327
-
lb
$(-3,000.0) - - $5,320
05 2.4133: Use most efficient type of electric motors $874 $2,248 $791
17,292
kWh
$83
-
kW-mo/yr
- - - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $3,559 $6,389 $3,221
70,047
kWh
$338
-
kW-mo/yr
- - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,114 $1,586 $1,912
41,618
kWh
$202
-
kW-mo/yr
- - - - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $1,407 $25 $1,274
27,843
kWh
$133
-
kW-mo/yr
- - - - -
09 2.4221: Install compressor air intakes in coolest locations $3,209 $1,110 $2,890
62,720
kWh
$319
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $123,343 $32,758 $25,611
557,152
kWh
$5,942
-
kW-mo/yr
$6,630
-
lb
$(-837.0) $71,892 $8,785 $5,320
TOTAL IMPLEMENTED $107,054 $14,611 $18,709
407,093
kWh
$5,202
-
kW-mo/yr
$303
-
lb
$2,163 $71,892 $8,785 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs