Assessment Year | 1997 |
---|---|
Principal Product | grain drying equipment |
NAICS |
n/a
|
SIC | 3556: Food Products Machinery |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
183,500
ft2
|
Annual Production | 15,200
pieces
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $23,022 | 903,576 |
kWh
|
$0.025 |
Electricity Demand | $29,173 | 4,044 |
kW-mo/yr
|
$7.21 |
Natural Gas | $45,772 | 8,710 |
MMBtu
|
$5.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,562 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,916 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8113: Purchase gas directly from a contract gas supplier | $15,243 | $4,200 | - | - |
$15,243
-
MMBtu
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,457 | $25,564 |
$2,861
112,251
kWh
|
$4,596
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.4322: Use or replace with energy efficient substitutes | $4,357 | $4,900 |
$405
15,826
kWh
|
$3,952
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.7314: Reduce ventilation air | $2,334 | $40 |
$17
586
kWh
|
$28
-
kW-mo/yr
|
$2,289
-
MMBtu
|
- | - | - | - | |
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,649 | $7,400 | - | - | - |
$2,064
-
lb
|
$(-1,000.0) | - | $585 | |
06 | 2.7243: Improve air circulation with destratification fans / other methods | $1,535 | $4,500 |
$(-308.0)
(-12,016)
kWh
|
$(-252.0)
-
kW-mo/yr
|
$2,095
-
MMBtu
|
- | - | - | - | |
07 | 3.7198: Reduce / eliminate use of disposable product | $4,866 | $2,300 | - | - | - |
$51
-
lb
|
$1,430 | $3,385 | - | |
08 | 4.211: Consider use / purchase of bulk materials where possible | $1,124 | - | - | - | - | - | $944 | $180 | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $665 | $110 |
$256
9,965
kWh
|
$409
-
kW-mo/yr
|
- | - | - | - | - | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $229 | $14 |
$64
2,638
kWh
|
$165
-
kW-mo/yr
|
- | - | - | - | - | |
11 | 2.4221: Install compressor air intakes in coolest locations | $103 | $205 |
$43
1,758
kWh
|
$60
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $39,562 | $49,233 |
$3,338
131,008
kWh
|
$8,958
-
kW-mo/yr
|
$19,627
-
MMBtu
|
$2,115
-
lb
|
$1,374 | $3,565 | $585 | ||
TOTAL IMPLEMENTED | $14,916 | $30,819 |
$3,582
140,386
kWh
|
$9,045
-
kW-mo/yr
|
$2,289
-
MMBtu
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs