ITAC Assessment: UD0764
ITAC logo
ITAC Assessment: UD0764
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Laminated fiberglass Truck caps and lids
NAICS 336214: Travel Trailer and Camper Manufacturing
SIC 3792: Travel Trailers and Campers
Sales Range $50
M
to 100
M
# of Employees 400
Plant Area 204,000
ft2
Annual Production 87,600
pieces
Production Hrs. Annual 5,100
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $429,469 6,687,200
kWh
Natural Gas $697,454 64,614
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $202,702 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $71,112

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
01 2.2414: Use waste heat from hot flue gases to preheat $101,033 $243,645 - - - $101,033
-
MMBtu
-
02 2.2511: Insulate bare equipment $35,952 $98,336 - - - $35,952
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $24,818 $49,600 $7,745
276,624
kWh
$16,396
-
kW-mo/yr
- - $677
04 2.3212: Optimize plant power factor $24,334 $6,000 - - $24,334 - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,675 $1,275 $1,652
58,650
kWh
$3,023
-
kW-mo/yr
- - -
06 2.7495: Install replacement doors $6,223 $13,000 - - - $6,223
-
MMBtu
-
07 2.7135: Install occupancy sensors $3,230 $760 $3,230
104,193
kWh
- - - -
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,437 - $868
28,002
kWh
$1,569
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $202,702 $412,616 $13,495
467,469
kWh
$20,988
-
kW-mo/yr
$24,334 $143,208
-
MMBtu
$677
TOTAL IMPLEMENTED $71,112 $149,971 $13,495
467,469
kWh
$20,988
-
kW-mo/yr
- $35,952
-
MMBtu
$677
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs