Assessment Year | 1996 |
---|---|
Principal Product | water and oil based paints |
NAICS |
n/a
|
SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
Sales Range | $10 M to 50M |
# of Employees | 35 |
Plant Area |
100,000
ft2
|
Annual Production | 2,000
Tgal
|
Production Hrs. Annual | 3,060
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $26,745 | 790,152 |
kWh
|
$0.034 |
Electricity Demand | $25,162 | 4,404 |
kW-mo/yr
|
$5.71 |
Natural Gas | $31,103 | 6,873 |
MMBtu
|
$4.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,364 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,000 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.4226: Use / purchase optimum sized compressor | $1,813 | $250 |
$1,103
31,653
kWh
|
$710
-
kW-mo/yr
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $1,578 | $200 |
$1,296
36,928
kWh
|
$282
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,264 | $250 |
$767
21,981
kWh
|
$497
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,736 | $7,752 |
$1,653
47,186
kWh
|
$1,083
-
kW-mo/yr
|
- | |
05 | 2.7135: Install occupancy sensors | $887 | $2,422 |
$501
14,361
kWh
|
$386
-
kW-mo/yr
|
- | |
06 | 3.5311: Recover and reuse waste material | $86 | - | - | - |
$86
-
lb
|
|
TOTAL RECOMMENDED | $8,364 | $10,874 |
$5,320
152,109
kWh
|
$2,958
-
kW-mo/yr
|
$86
-
lb
|
||
TOTAL IMPLEMENTED | $4,000 | $8,002 |
$2,420
69,167
kWh
|
$1,580
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs