| Assessment Year | 1996 |
|---|---|
| Principal Product | Custom Plastic Moldings |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 95 |
| Plant Area |
35,000
ft2
|
| Annual Production | 1,250,000
lb
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | Nebraska |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $99,601 | 2,078,839 |
kWh
|
$0.048 |
| Electricity Demand | $4,975 | 5,616 |
kW-mo/yr
|
$0.89 |
| Electricity Fees | $2,274 | - |
|
- |
| Natural Gas | $6,847 | 1,907 |
MMBtu
|
$3.59 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $4,652 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,207 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,007 | $50 |
$2,902
60,668
kWh
|
$105
-
kW-mo/yr
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $660 | $217 |
$638
13,189
kWh
|
$22
-
kW-mo/yr
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $540 | $169 |
$521
10,844
kWh
|
$19
-
kW-mo/yr
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $296 | $268 |
$286
5,862
kWh
|
$10
-
kW-mo/yr
|
- | |
| 05 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $149 | $100 | - | - |
$149
-
lb
|
|
| TOTAL RECOMMENDED | $4,652 | $804 |
$4,347
90,563
kWh
|
$156
-
kW-mo/yr
|
$149
-
lb
|
||
| TOTAL IMPLEMENTED | $4,207 | $436 |
$4,061
84,701
kWh
|
$146
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs