| Assessment Year | 1996 |
|---|---|
| Principal Product | Sign Letters |
| NAICS |
n/a
|
| SIC | 3079: |
| Sales Range | $10 M to 50M |
| # of Employees | 110 |
| Plant Area |
80,000
ft2
|
| Annual Production | 1,400,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $82,634 | 3,180,246 |
kWh
|
$0.026 |
| Electricity Demand | $83,525 | 11,808 |
kW-mo/yr
|
$7.07 |
| Electricity Fees | $3,803 | - |
|
- |
| Natural Gas | $9,060 | 2,250 |
MMBtu
|
$4.03 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $6,335 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,893 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3191: Use demand controller or load shedder | $2,323 | - | - |
$2,323
-
kW-mo/yr
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,297 | $63 |
$838
32,239
kWh
|
$459
-
kW-mo/yr
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $350 | $262 |
$231
8,792
kWh
|
$119
-
kW-mo/yr
|
- | |
| 04 | 2.7135: Install occupancy sensors | $900 | $1,362 |
$526
20,223
kWh
|
$374
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $346 | $444 |
$212
8,206
kWh
|
$134
-
kW-mo/yr
|
- | |
| 06 | 2.2511: Insulate bare equipment | $466 | $92 |
$177
6,741
kWh
|
$289
-
kW-mo/yr
|
- | |
| 07 | 3.1161: Eliminate/reduce an operation | $653 | $574 | - | - |
$653
-
lb
|
|
| TOTAL RECOMMENDED | $6,335 | $2,797 |
$1,984
76,201
kWh
|
$3,698
-
kW-mo/yr
|
$653
-
lb
|
||
| TOTAL IMPLEMENTED | $2,893 | $2,131 |
$1,807
69,460
kWh
|
$1,086
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs