Assessment Year | 1996 |
---|---|
Principal Product | Sign Letters |
NAICS |
n/a
|
SIC | 3079: |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
80,000
ft2
|
Annual Production | 1,400,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $82,634 | 3,180,246 |
kWh
|
$0.026 |
Electricity Demand | $83,525 | 11,808 |
kW-mo/yr
|
$7.07 |
Electricity Fees | $3,803 | - |
|
- |
Natural Gas | $9,060 | 2,250 |
MMBtu
|
$4.03 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,335 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,893 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $2,323 | - | - |
$2,323
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,297 | $63 |
$838
32,239
kWh
|
$459
-
kW-mo/yr
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $350 | $262 |
$231
8,792
kWh
|
$119
-
kW-mo/yr
|
- | |
04 | 2.7135: Install occupancy sensors | $900 | $1,362 |
$526
20,223
kWh
|
$374
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $346 | $444 |
$212
8,206
kWh
|
$134
-
kW-mo/yr
|
- | |
06 | 2.2511: Insulate bare equipment | $466 | $92 |
$177
6,741
kWh
|
$289
-
kW-mo/yr
|
- | |
07 | 3.1161: Eliminate/reduce an operation | $653 | $574 | - | - |
$653
-
lb
|
|
TOTAL RECOMMENDED | $6,335 | $2,797 |
$1,984
76,201
kWh
|
$3,698
-
kW-mo/yr
|
$653
-
lb
|
||
TOTAL IMPLEMENTED | $2,893 | $2,131 |
$1,807
69,460
kWh
|
$1,086
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs