ITAC Assessment: IA0142
ITAC logo
ITAC Assessment: IA0142
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Sign Letters
NAICS
n/a
SIC 3079:
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 80,000
ft2
Annual Production 1,400,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $82,634 3,180,246
kWh
Electricity Demand $83,525 11,808
kW-mo/yr
Electricity Fees $3,803 -
Natural Gas $9,060 2,250
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,335 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,893

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (haz) Savings
01 2.3191: Use demand controller or load shedder $2,323 - - $2,323
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,297 $63 $838
32,239
kWh
$459
-
kW-mo/yr
-
03 2.4221: Install compressor air intakes in coolest locations $350 $262 $231
8,792
kWh
$119
-
kW-mo/yr
-
04 2.7135: Install occupancy sensors $900 $1,362 $526
20,223
kWh
$374
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $346 $444 $212
8,206
kWh
$134
-
kW-mo/yr
-
06 2.2511: Insulate bare equipment $466 $92 $177
6,741
kWh
$289
-
kW-mo/yr
-
07 3.1161: Eliminate/reduce an operation $653 $574 - - $653
-
lb
TOTAL RECOMMENDED $6,335 $2,797 $1,984
76,201
kWh
$3,698
-
kW-mo/yr
$653
-
lb
TOTAL IMPLEMENTED $2,893 $2,131 $1,807
69,460
kWh
$1,086
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs