Assessment Year | 1995 |
---|---|
Principal Product | Hydraulic cylinders |
NAICS |
n/a
|
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 235 |
Plant Area |
180,000
ft2
|
Annual Production | 240,000
pieces
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $175,707 | 4,388,335 |
kWh
|
$0.040 |
Natural Gas | $65,864 | 21,668 |
MMBtu
|
$3.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,819 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,530 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,157 | $22,800 |
$8,157
197,538
kWh
|
- | - | |
02 | 2.6218: Turn off equipment when not in use | $607 | - |
$607
17,585
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,470 | $342 |
$3,470
86,753
kWh
|
- | - | |
04 | 2.2437: Recover waste heat from equipment | $1,472 | $2,090 | - |
$1,472
-
MMBtu
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $944 | $165 |
$944
23,740
kWh
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $769 | $25 |
$769
19,343
kWh
|
- | - | |
07 | 2.4133: Use most efficient type of electric motors | $1,903 | $669 |
$1,903
47,479
kWh
|
- | - | |
08 | 2.1213: Direct warmest air to combustion intake | $1,249 | $1,030 | - |
$1,249
-
MMBtu
|
- | |
09 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $6,542 | $34,200 | - |
$6,542
-
MMBtu
|
- | |
10 | 3.1191: Change procedures / equipment / operating conditions | $8,419 | $5,456 | - | - |
$8,419
-
lb
|
|
11 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,287 | - | - | - |
$1,287
-
lb
|
|
TOTAL RECOMMENDED | $34,819 | $66,777 |
$15,850
392,438
kWh
|
$9,263
-
MMBtu
|
$9,706
-
lb
|
||
TOTAL IMPLEMENTED | $16,530 | $38,331 |
$5,980
151,817
kWh
|
$9,263
-
MMBtu
|
$1,287
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs