| Assessment Year | 2014 |
|---|---|
| Principal Product | Metal building components |
| NAICS | 332311: Prefabricated Metal Building and Component Manufacturing |
| SIC | 3448: Prefabricated Metal Buildings and Components |
| Sales Range | $100 M to 500M |
| # of Employees | 135 |
| Plant Area |
122,000
ft2
|
| Annual Production | 120,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $100,965 | 2,022,269 |
kWh
|
$0.050 |
| Electricity Demand | $35,067 | 5,193 |
kW-mo/yr
|
$6.75 |
| Natural Gas | $31,752 | 4,145 |
MMBtu
|
$7.66 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $26,719 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,712 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,648 | $3,905 |
$1,332
26,696
kWh
|
$316
-
kW-mo/yr
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,062 | $9,740 |
$2,062
41,315
kWh
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $506 | $594 |
$506
10,150
kWh
|
- | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,496 | $1,342 |
$3,496
70,060
kWh
|
- | - | - | |
| 05 | 2.8121: Apply for tax-free status for energy purchases | $4,508 | $140 | - | - | - | $4,508 | |
| 06 | 2.5113: Use direct flame impingement or infrared processing for chamber type heating | $14,499 | $12,962 | - | - |
$14,499
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $26,719 | $28,683 |
$7,396
148,221
kWh
|
$316
-
kW-mo/yr
|
$14,499
-
MMBtu
|
$4,508 | ||
| TOTAL IMPLEMENTED | $7,712 | $15,581 |
$7,396
148,221
kWh
|
$316
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs