| Assessment Year | 1995 |
|---|---|
| Principal Product | hubs, spindles, rims, wheels |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $50 M to 100M |
| # of Employees | 165 |
| Plant Area |
112,653
ft2
|
| Annual Production | 1,770,000
pieces
|
| Production Hrs. Annual | 4,188
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $241,914 | 4,339,684 |
kWh
|
$0.056 |
| Natural Gas | $59,269 | 20,637 |
MMBtu
|
$2.87 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $26,975 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,489 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $4,440 | $1,537 |
$4,440
79,719
kWh
|
- | - | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $1,564 | $135 |
$1,564
28,136
kWh
|
- | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $758 | $25 |
$758
13,482
kWh
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $815 | $250 |
$815
14,654
kWh
|
- | - | |
| 05 | 2.6212: Turn off equipment during breaks, reduce operating time | $510 | $25 |
$510
9,086
kWh
|
- | - | |
| 06 | 2.2515: Use optimum thickness insulation | $303 | $1,020 | - |
$303
-
MMBtu
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $948 | $169 |
$948
16,999
kWh
|
- | - | |
| 08 | 2.7135: Install occupancy sensors | $784 | $920 |
$784
14,068
kWh
|
- | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $909 | $1,570 |
$909
16,413
kWh
|
- | - | |
| 10 | 3.3128: Utilize other methods to remove contaminants | $15,944 | $2,290 | - | - |
$15,944
-
lb
|
|
| TOTAL RECOMMENDED | $26,975 | $7,941 |
$10,728
192,557
kWh
|
$303
-
MMBtu
|
$15,944
-
lb
|
||
| TOTAL IMPLEMENTED | $9,489 | $4,706 |
$9,186
165,007
kWh
|
$303
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs