| Assessment Year | 1995 |
|---|---|
| Principal Product | bags |
| NAICS |
n/a
|
| SIC | 2673: Plastics, Foil, and Coated Paper Bags |
| Sales Range | $10 M to 50M |
| # of Employees | 230 |
| Plant Area |
124,400
ft2
|
| Annual Production | 277,700,000
pieces
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $136,664 | 2,781,067 |
kWh
|
$0.049 |
| Natural Gas | $22,532 | 5,196 |
MMBtu
|
$4.34 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $80,440 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $57,110 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $14,717 | $25,220 |
$14,717
259,965
kWh
|
- | - | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $12,263 | $1,888 |
$12,263
216,589
kWh
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,614 | $4,330 |
$1,614
28,429
kWh
|
- | - | |
| 04 | 2.2437: Recover waste heat from equipment | $957 | $610 | - |
$957
-
MMBtu
|
- | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,175 | $485 |
$1,175
20,516
kWh
|
- | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,004 | $25 |
$1,004
17,878
kWh
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,861 | $12,260 |
$4,861
85,873
kWh
|
- | - | |
| 08 | 2.7111: Reduce illumination to minimum necessary levels | $3,388 | $425 |
$3,388
58,910
kWh
|
- | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,047 | $2,700 |
$1,047
18,464
kWh
|
- | - | |
| 10 | 2.7135: Install occupancy sensors | $487 | $1,470 |
$487
8,499
kWh
|
- | - | |
| 11 | 2.6214: Shut off pilots in standby equipment | $280 | $50 | - |
$280
-
MMBtu
|
- | |
| 12 | 2.7224: Reduce space conditioning during non-working hours | $237 | - |
$237
4,103
kWh
|
- | - | |
| 13 | 3.1175: Use a different or recycled raw material | $38,410 | - | - | - |
$38,410
-
lb
|
|
| TOTAL RECOMMENDED | $80,440 | $49,463 |
$40,793
719,226
kWh
|
$1,237
-
MMBtu
|
$38,410
-
lb
|
||
| TOTAL IMPLEMENTED | $57,110 | $30,645 |
$17,743
313,013
kWh
|
$957
-
MMBtu
|
$38,410
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs