| Assessment Year | 1994 |
|---|---|
| Principal Product | automotive stampings |
| NAICS |
n/a
|
| SIC | 3465: Automotive Stampings |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
73,250
ft2
|
| Annual Production | 450,000
lb
|
| Production Hrs. Annual | 6,360
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $179,050 | 3,086,460 |
kWh
|
$0.058 |
| Natural Gas | $25,179 | 5,764 |
MMBtu
|
$4.37 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $56,018 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $44,728 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.6212: Turn off equipment during breaks, reduce operating time | $22,684 | - |
$22,684
390,973
kWh
|
- | - | |
| 02 | 2.2437: Recover waste heat from equipment | $11,414 | $1,400 | - |
$11,414
-
MMBtu
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,352 | $500 |
$2,352
40,445
kWh
|
- | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $8,278 | $2,340 |
$8,278
142,732
kWh
|
- | - | |
| 05 | 2.8114: Change rate schedules or other changes in utility service | $4,683 | - | - | - | $4,683 | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,924 | $1,028 |
$3,924
67,702
kWh
|
- | - | |
| 07 | 2.7135: Install occupancy sensors | $947 | $693 |
$947
16,413
kWh
|
- | - | |
| 08 | 2.7261: Install timers and/or thermostats | $1,201 | $1,300 |
$1,034
17,878
kWh
|
$167
-
MMBtu
|
- | |
| 09 | 2.6212: Turn off equipment during breaks, reduce operating time | $535 | - |
$535
9,379
kWh
|
- | - | |
| TOTAL RECOMMENDED | $56,018 | $7,261 |
$39,754
685,522
kWh
|
$11,581
-
MMBtu
|
$4,683 | ||
| TOTAL IMPLEMENTED | $44,728 | $4,240 |
$33,314
574,150
kWh
|
$11,414
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs