ITAC Assessment: OD0174
ITAC logo
ITAC Assessment: OD0174
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Paper
NAICS
n/a
SIC 2621: Paper Mills
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 160,000
ft2
Annual Production 0
units
Production Hrs. Annual 8,064
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $411,551 20,159,244
kWh
Electricity Demand $424,691 37,632
kW-mo/yr
Electricity Fees $102,448 -
Natural Gas $169,169 57,663
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,801 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,705 $2,700 $1,705
83,550
kWh
- -
02 2.1233: Analyze flue gas for proper air/fuel ratio $864 $1,000 - $864
-
MMBtu
-
03 2.7224: Reduce space conditioning during non-working hours $1,307 $2,000 $239
11,734
kWh
$1,068
-
MMBtu
-
04 3.4155: Meter waste water $4,925 $2,156 - - $4,925
-
Tgal
TOTAL RECOMMENDED $8,801 $7,856 $1,944
95,284
kWh
$1,932
-
MMBtu
$4,925
-
Tgal
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs