Assessment Year | 1994 |
---|---|
Principal Product | heat transfer equipment |
NAICS |
n/a
|
SIC | 3519: Internal Combustion Engines, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
160,000
ft2
|
Annual Production | 2,500,000
ton
|
Production Hrs. Annual | 4,875
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $259,733 | 7,464,830 |
kWh
|
$0.035 |
Natural Gas | $57,166 | 17,262 |
MMBtu
|
$3.31 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $28,181 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,182 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,198 | $350 |
$11,198
321,805
kWh
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $1,811 | $365 |
$1,811
52,169
kWh
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,098 | $25 |
$1,098
31,653
kWh
|
- | |
04 | 2.2514: Cover open tanks | $1,597 | $3,050 | - |
$1,597
-
MMBtu
|
|
05 | 2.6212: Turn off equipment during breaks, reduce operating time | $6,971 | - | - |
$6,971
-
MMBtu
|
|
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,536 | $7,244 |
$4,536
130,422
kWh
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $522 | $771 |
$522
14,947
kWh
|
- | |
08 | 2.7135: Install occupancy sensors | $448 | $1,067 |
$448
12,896
kWh
|
- | |
TOTAL RECOMMENDED | $28,181 | $12,872 |
$19,613
563,892
kWh
|
$8,568
-
MMBtu
|
||
TOTAL IMPLEMENTED | $16,182 | $8,661 |
$16,182
465,123
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs