ITAC Assessment: IA0096
ITAC logo
ITAC Assessment: IA0096
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product heat transfer equipment
NAICS
n/a
SIC 3519: Internal Combustion Engines, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 160,000
ft2
Annual Production 2,500,000
ton
Production Hrs. Annual 4,875
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $259,733 7,464,830
kWh
Natural Gas $57,166 17,262
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $28,181 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,182

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $11,198 $350 $11,198
321,805
kWh
-
02 2.4221: Install compressor air intakes in coolest locations $1,811 $365 $1,811
52,169
kWh
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,098 $25 $1,098
31,653
kWh
-
04 2.2514: Cover open tanks $1,597 $3,050 - $1,597
-
MMBtu
05 2.6212: Turn off equipment during breaks, reduce operating time $6,971 - - $6,971
-
MMBtu
06 2.7142: Utilize higher efficiency lamps and/or ballasts $4,536 $7,244 $4,536
130,422
kWh
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $522 $771 $522
14,947
kWh
-
08 2.7135: Install occupancy sensors $448 $1,067 $448
12,896
kWh
-
TOTAL RECOMMENDED $28,181 $12,872 $19,613
563,892
kWh
$8,568
-
MMBtu
TOTAL IMPLEMENTED $16,182 $8,661 $16,182
465,123
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs