ITAC Assessment: MA0459
ITAC logo
ITAC Assessment: MA0459
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Pressure Sensitive Adhesives on Various Substrates
NAICS
n/a
SIC 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 47
Plant Area 44,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,142
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,116 518,464
kWh
Electricity Demand $12,147 1,987
kW-mo/yr
Electricity Fees $167 -
Natural Gas $90,902 21,012
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,676 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,908

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
01 3.1191: Change procedures / equipment / operating conditions $2,945 $7,695 $500
9,379
kWh
$414
-
kW-mo/yr
- $2,031
-
Tgal
02 2.7224: Reduce space conditioning during non-working hours $1,064 $150 $983
18,464
kWh
- $81
-
MMBtu
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $789 $150 $789
13,775
kWh
- - -
04 2.3212: Optimize plant power factor $557 $1,275 - $557
-
kW-mo/yr
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $266 $1,250 $266
4,982
kWh
- - -
06 2.7135: Install occupancy sensors $55 $248 $55
1,172
kWh
- - -
TOTAL RECOMMENDED $5,676 $10,768 $2,593
47,772
kWh
$971
-
kW-mo/yr
$81
-
MMBtu
$2,031
-
Tgal
TOTAL IMPLEMENTED $1,908 $548 $1,827
33,411
kWh
- $81
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs