| Assessment Year | 2000 |
|---|---|
| Principal Product | Pressure Sensitive Adhesives on Various Substrates |
| NAICS |
n/a
|
| SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 47 |
| Plant Area |
44,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,142
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $31,116 | 518,464 |
kWh
|
$0.060 |
| Electricity Demand | $12,147 | 1,987 |
kW-mo/yr
|
$6.11 |
| Electricity Fees | $167 | - |
|
- |
| Natural Gas | $90,902 | 21,012 |
MMBtu
|
$4.33 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $5,676 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,908 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.1191: Change procedures / equipment / operating conditions | $2,945 | $7,695 |
$500
9,379
kWh
|
$414
-
kW-mo/yr
|
- |
$2,031
-
Tgal
|
|
| 02 | 2.7224: Reduce space conditioning during non-working hours | $1,064 | $150 |
$983
18,464
kWh
|
- |
$81
-
MMBtu
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $789 | $150 |
$789
13,775
kWh
|
- | - | - | |
| 04 | 2.3212: Optimize plant power factor | $557 | $1,275 | - |
$557
-
kW-mo/yr
|
- | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $266 | $1,250 |
$266
4,982
kWh
|
- | - | - | |
| 06 | 2.7135: Install occupancy sensors | $55 | $248 |
$55
1,172
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $5,676 | $10,768 |
$2,593
47,772
kWh
|
$971
-
kW-mo/yr
|
$81
-
MMBtu
|
$2,031
-
Tgal
|
||
| TOTAL IMPLEMENTED | $1,908 | $548 |
$1,827
33,411
kWh
|
- |
$81
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs