ITAC Assessment: IA0079
ITAC logo
ITAC Assessment: IA0079
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product scales and weighing apparatus
NAICS
n/a
SIC 3596: Scales and Balances, Except Laboratory
Sales Range $10
M
to 50
M
# of Employees 295
Plant Area 167,000
ft2
Annual Production 250,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $227,794 3,687,280
kWh
Natural Gas $27,132 7,381
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,125 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,047

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $18,038 $39,492 $18,038
291,911
kWh
-
02 2.7135: Install occupancy sensors $1,520 $2,683 $1,520
24,619
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $239 $537 $239
3,810
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $1,195 $136 $1,195
19,343
kWh
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $852 $45 $852
13,775
kWh
-
06 2.8113: Purchase gas directly from a contract gas supplier $4,281 $4,200 - $4,281
TOTAL RECOMMENDED $26,125 $47,093 $21,844
353,458
kWh
$4,281
TOTAL IMPLEMENTED $2,047 $181 $2,047
33,118
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs