| Assessment Year | 1993 |
|---|---|
| Principal Product | URETHANNE FOAM PRODUCTS |
| NAICS |
n/a
|
| SIC | 3086: Plastics Foam Products |
| Sales Range | $10 M to 50M |
| # of Employees | 400 |
| Plant Area |
n/a
|
| Annual Production | 1,000,000
lb
|
| Production Hrs. Annual | 4,862
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $196,091 | 3,276,084 |
kWh
|
$0.060 |
| Natural Gas | $34,834 | 8,249 |
MMBtu
|
$4.22 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $10,065 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,873 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $661 | $2,199 |
$661
11,137
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,117 | - |
$2,721
45,428
kWh
|
- | $(-604.0) | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $990 | $3,600 |
$990
16,413
kWh
|
- | - | |
| 04 | 2.7135: Install occupancy sensors | $955 | $1,585 |
$955
15,826
kWh
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $130 | $300 |
$130
2,052
kWh
|
- | - | |
| 06 | 2.2691: Shut off cooling if cold outside air will cool process | $1,954 | $10,280 |
$1,954
33,411
kWh
|
- | - | |
| 07 | 2.7243: Improve air circulation with destratification fans / other methods | $1,942 | $4,750 |
$(-581.0)
(-9,672)
kWh
|
$2,523
-
MMBtu
|
- | |
| 08 | 2.7261: Install timers and/or thermostats | $1,316 | $1,350 |
$528
8,792
kWh
|
$788
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $10,065 | $24,064 |
$7,358
123,387
kWh
|
$3,311
-
MMBtu
|
$(-604.0) | ||
| TOTAL IMPLEMENTED | $5,873 | $18,579 |
$2,562
43,668
kWh
|
$3,311
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs