Assessment Year | 2023 |
---|---|
Principal Product | Steel roller bearing component |
NAICS | 331110: Iron and Steel Mills and Ferroalloy Manufacturing |
SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
Sales Range | $100 M to 500M |
# of Employees | 56 |
Plant Area |
217,000
ft2
|
Annual Production | 10,000,000
pieces
|
Production Hrs. Annual | 4,200
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $550,000 | 14,435,695 |
kWh
|
$0.038 | |
Natural Gas | $300,000 | 45,175 |
MMBtu
|
$6.64 | |
Waste Disposal Costs | |||||
Water Usage | $25,000 | 9 |
Tgal
|
$2,880.18 | |
Other Liquid (haz) | $65,000 | 5,000 |
gal
|
$13.00 | |
Solid Waste (haz) | $65,000 | 1,000 |
lb
|
$65.00 | |
TOTAL YEARLY COSTS | $1,005,000 | ||||
RECOMMENDED SAVINGS* | $234,241 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|
01 | 2.4224: Upgrade controls on compressors | $5,763 | $4,760 |
$5,763
151,657
kWh
|
- | |
02 | 4.212: Adopt in-house material generation | $215,269 | $246,950 |
$(-9,731.1)
(-256,080)
kWh
|
$225,000 | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $956 | $400 |
$956
25,080
kWh
|
- | |
04 | 2.4224: Upgrade controls on compressors | $2,001 | $8,583 |
$2,001
52,522
kWh
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,453 | $225 |
$1,453
38,124
kWh
|
- | |
06 | 4.652: Replace existing equipment with more suitable substitutes | $8,800 | $26,211 |
$8,800
230,964
kWh
|
- | |
TOTAL RECOMMENDED | $234,241 | $287,129 |
$9,241
242,267
kWh
|
$225,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs