ITAC Assessment: IA0243
ITAC logo
ITAC Assessment: IA0243
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product athletic socks
NAICS
n/a
SIC 2252: Hosiery, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 350
Plant Area 150,000
ft2
Annual Production 19,200,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $193,200 6,856,975
kWh
Electricity Demand $65,820 16,416
kW-mo/yr
Natural Gas $88,445 25,000
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,881 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,527

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,163 $616 $3,267
116,354
kWh
$896
-
kW-mo/yr
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,274 $50 $999
35,463
kWh
$275
-
kW-mo/yr
- -
03 2.4133: Use most efficient type of electric motors $1,742 - $1,366
48,652
kWh
$376
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,660 $2,661 $2,087
74,150
kWh
$573
-
kW-mo/yr
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,229 - $964
34,291
kWh
$265
-
kW-mo/yr
- -
06 3.4113: Treat and reuse rinse waters $4,393 $4,718 - - $4,393
-
Tgal
-
07 4.211: Consider use / purchase of bulk materials where possible $3,420 $2,950 - - - $3,420
TOTAL RECOMMENDED $18,881 $10,995 $8,683
308,910
kWh
$2,385
-
kW-mo/yr
$4,393
-
Tgal
$3,420
TOTAL IMPLEMENTED $11,527 $5,334 $5,597
199,297
kWh
$1,537
-
kW-mo/yr
$4,393
-
Tgal
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs