| Assessment Year | 1993 |
|---|---|
| Principal Product | poultry products |
| NAICS |
n/a
|
| SIC | 2013: Sausages and Other Prepared Meat Products |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
171,090
ft2
|
| Annual Production | 21,331
ton
|
| Production Hrs. Annual | 4,290
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $137,497 | 3,314,478 |
kWh
|
$0.041 |
| Natural Gas | $81,415 | 16,996 |
MMBtu
|
$4.79 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $47,955 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $34,406 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.8113: Purchase gas directly from a contract gas supplier | $27,024 | $4,200 | - | - | $27,024 | |
| 02 | 2.8121: Apply for tax-free status for energy purchases | $9,529 | $250 | - | - | $9,529 | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,185 | $100 |
$4,185
100,821
kWh
|
- | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,109 | $1,500 |
$1,109
26,671
kWh
|
- | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $409 | $175 |
$409
9,965
kWh
|
- | - | |
| 06 | 2.2437: Recover waste heat from equipment | $229 | $486 | - |
$229
-
MMBtu
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,922 | $1,083 |
$1,922
46,307
kWh
|
- | - | |
| 08 | 2.7135: Install occupancy sensors | $1,689 | $3,327 |
$1,689
40,739
kWh
|
- | - | |
| 09 | 2.3212: Optimize plant power factor | $1,859 | $6,615 |
$1,859
-
kWh
|
- | - | |
| TOTAL RECOMMENDED | $47,955 | $17,736 |
$11,173
224,503
kWh
|
$229
-
MMBtu
|
$36,553 | ||
| TOTAL IMPLEMENTED | $34,406 | $12,901 |
$7,153
127,492
kWh
|
$229
-
MMBtu
|
$27,024 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs