| Assessment Year | 1993 |
|---|---|
| Principal Product | livestock waterers & ag sprayers |
| NAICS |
n/a
|
| SIC | 3523: Farm Machinery and Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 106 |
| Plant Area |
144,000
ft2
|
| Annual Production | 29,930
pieces
|
| Production Hrs. Annual | 2,125
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $111,360 | 1,325,615 |
kWh
|
$0.084 |
| Natural Gas | $26,180 | 7,928 |
MMBtu
|
$3.30 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $9,647 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,841 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,522 | $100 |
$2,522
29,894
kWh
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $490 | $200 |
$490
5,862
kWh
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,059 | $20 |
$1,059
12,603
kWh
|
- | |
| 04 | 2.7243: Improve air circulation with destratification fans / other methods | $4,409 | $6,400 | - |
$4,409
-
MMBtu
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $394 | $1,752 |
$394
4,103
kWh
|
- | |
| 06 | 2.7135: Install occupancy sensors | $257 | $270 |
$257
2,931
kWh
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $196 | $321 |
$196
2,345
kWh
|
- | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $320 | $280 |
$320
3,810
kWh
|
- | |
| TOTAL RECOMMENDED | $9,647 | $9,343 |
$5,238
61,548
kWh
|
$4,409
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $7,841 | $8,853 |
$3,432
40,152
kWh
|
$4,409
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs