ITAC Assessment: CO0500
ITAC logo
ITAC Assessment: CO0500
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Finished metal products
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $1
M
to 5
M
# of Employees 35
Plant Area 58,500
ft2
Annual Production 120,000
pieces
Production Hrs. Annual 2,730
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $21,974 1,327,589
kWh
Electricity Demand $73,284 5,447
kW-mo/yr
Electricity Fees $193 -
Natural Gas $80,590 12,347
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $42,840 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $39,010

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $29,000 $7,000 - $29,000
-
kW-mo/yr
- - - -
02 2.8114: Change rate schedules or other changes in utility service $8,990 $300 - - - - $8,990 -
03 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system $2,640 $5,750 $520
31,100
kWh
$2,120
-
kW-mo/yr
- - - -
04 2.2511: Insulate bare equipment $1,110 $4,890 - - $1,110
-
MMBtu
- - -
05 2.2511: Insulate bare equipment $730 $300 - - $730
-
MMBtu
- - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $290 $50 $60
3,900
kWh
$230
-
kW-mo/yr
- - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $80 - $200
11,900
kWh
$710
-
kW-mo/yr
- $(-310.0) - $(-520.0)
TOTAL RECOMMENDED $42,840 $18,290 $780
46,900
kWh
$32,060
-
kW-mo/yr
$1,840
-
MMBtu
$(-310.0) $8,990 $(-520.0)
TOTAL IMPLEMENTED $39,010 $7,650 $60
3,900
kWh
$29,230
-
kW-mo/yr
$730
-
MMBtu
- $8,990 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs