| Assessment Year | 2000 |
|---|---|
| Principal Product | Extruded Plastics |
| NAICS |
n/a
|
| SIC | 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
50,000
ft2
|
| Annual Production | 2,000,000
lb
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $96,559 | 1,865,475 |
kWh
|
$0.052 |
| Electricity Demand | $127,593 | 6,874 |
kW-mo/yr
|
$18.56 |
| Electricity Fees | $27,812 | - |
|
- |
| LPG | $3,464 | 371 |
MMBtu
|
$9.34 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $24,826 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,840 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $845 | $2,289 |
$268
5,275
kWh
|
$577
-
kW-mo/yr
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $736 | $800 |
$250
4,982
kWh
|
$486
-
kW-mo/yr
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $702 | $60 |
$457
8,792
kWh
|
$245
-
kW-mo/yr
|
- | |
| 04 | 2.4239: Eliminate or reduce compressed air usage | $2,736 | $1,200 |
$2,736
53,048
kWh
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,502 | $600 | - | - | $5,502 | |
| 06 | 4.611: Begin a practice of predictive / preventative maintenance | $840 | $200 | - | - | $840 | |
| 07 | 4.611: Begin a practice of predictive / preventative maintenance | $840 | $250 | - | - | $840 | |
| 08 | 4.423: Move product using mechanical means | $1,220 | $40 | - | - | $1,220 | |
| 09 | 4.514: Re-arrange equipment layout to reduce handling costs | $1,313 | $400 | - | - | $1,313 | |
| 10 | 3.1191: Change procedures / equipment / operating conditions | $10,092 | $6,500 | - | - | $10,092 | |
| TOTAL RECOMMENDED | $24,826 | $12,339 |
$3,711
72,097
kWh
|
$1,308
-
kW-mo/yr
|
$19,807 | ||
| TOTAL IMPLEMENTED | $11,840 | $2,350 |
$3,193
61,840
kWh
|
$245
-
kW-mo/yr
|
$8,402 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs