ITAC Assessment: HO0238
ITAC logo
ITAC Assessment: HO0238
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Extruded Plastics
NAICS
n/a
SIC 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 50,000
ft2
Annual Production 2,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $96,559 1,865,475
kWh
Electricity Demand $127,593 6,874
kW-mo/yr
Electricity Fees $27,812 -
LPG $3,464 371
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,826 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,840

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $845 $2,289 $268
5,275
kWh
$577
-
kW-mo/yr
-
02 2.4221: Install compressor air intakes in coolest locations $736 $800 $250
4,982
kWh
$486
-
kW-mo/yr
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $702 $60 $457
8,792
kWh
$245
-
kW-mo/yr
-
04 2.4239: Eliminate or reduce compressed air usage $2,736 $1,200 $2,736
53,048
kWh
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,502 $600 - - $5,502
06 4.611: Begin a practice of predictive / preventative maintenance $840 $200 - - $840
07 4.611: Begin a practice of predictive / preventative maintenance $840 $250 - - $840
08 4.423: Move product using mechanical means $1,220 $40 - - $1,220
09 4.514: Re-arrange equipment layout to reduce handling costs $1,313 $400 - - $1,313
10 3.1191: Change procedures / equipment / operating conditions $10,092 $6,500 - - $10,092
TOTAL RECOMMENDED $24,826 $12,339 $3,711
72,097
kWh
$1,308
-
kW-mo/yr
$19,807
TOTAL IMPLEMENTED $11,840 $2,350 $3,193
61,840
kWh
$245
-
kW-mo/yr
$8,402
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs