ITAC Assessment: HO0236
ITAC logo
ITAC Assessment: HO0236
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Decorative Ornamental Figurines
NAICS
n/a
SIC 3999: Manufacturing Industries, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 90,000
ft2
Annual Production 650,000
pieces
Production Hrs. Annual 2,805
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $44,637 1,033,705
kWh
Electricity Demand $66,560 3,333
kW-mo/yr
Electricity Fees $1,528 -
Natural Gas $9,848 1,272
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $441,316 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
01 2.7135: Install occupancy sensors $3,159 $2,800 n/a $3,159
22,567
kWh
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $402 $15 n/a $135
3,224
kWh
$267
-
kW-mo/yr
-
03 2.4221: Install compressor air intakes in coolest locations $332 $400 n/a $111
2,638
kWh
$221
-
kW-mo/yr
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,167 $120 n/a $1,167
9,086
kWh
- -
05 2.8114: Change rate schedules or other changes in utility service $4,374 $20,000 n/a - - $4,374
06 2.8113: Purchase gas directly from a contract gas supplier $985 $250 n/a - - $985
07 4.322: Eliminate old stock and modify inventory control $7,650 $5,000 n/a - - $7,650
08 4.321: Optimize production lot sizes and inventories $1,912 $5,880 n/a - - $1,912
09 4.424: Improve space comfort conditioning $1,160 $335 n/a - - $1,160
10 4.114: Add/modify equipment to improve drying process $419,000 $30,000 n/a - - $419,000
11 3.4155: Meter waste water $1,000 $250 n/a - - $1,000
12 3.5212: Regrind, reuse, or sell scrap plastic parts $175 $500 n/a - - $175
TOTAL RECOMMENDED $441,316 $65,550 $4,572
37,515
kWh
$488
-
kW-mo/yr
$436,256
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs