ITAC Assessment: HO0234
ITAC logo
ITAC Assessment: HO0234
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Glass Containers
NAICS
n/a
SIC 3221: Glass Containers
Sales Range n/a
# of Employees 298
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 8,760
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Natural Gas $1,871,036 482,610
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $53,167 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings One-time Revenue or Avoided Cost Savings
01 2.4221: Install compressor air intakes in coolest locations $29,037 $14,400 n/a $29,037
206,800
kWh
-
02 4.124: Install continuous lubrication equipment $5,850 $20,000 n/a - $5,850
03 4.114: Add/modify equipment to improve drying process $11,460 - n/a - $11,460
04 4.424: Improve space comfort conditioning $500 $500 n/a - $500
05 4.611: Begin a practice of predictive / preventative maintenance $3,360 $300 n/a - $3,360
06 4.424: Improve space comfort conditioning $2,960 - n/a - $2,960
TOTAL RECOMMENDED $53,167 $35,200 $29,037
206,800
kWh
$24,130
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs