| Assessment Year | 1999 |
|---|---|
| Principal Product | Hermetic Seals |
| NAICS |
n/a
|
| SIC | 3679: Electronic Components, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
33,000
ft2
|
| Annual Production | 20,000
lb
|
| Production Hrs. Annual | 3,050
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $95,666 | 1,061,841 |
kWh
|
$0.090 |
| Electricity Demand | $39,197 | 5,200 |
kW-mo/yr
|
$7.54 |
| Electricity Fees | $(-8,121.0) | - |
|
- |
| Natural Gas | $26,296 | 4,098 |
MMBtu
|
$6.42 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $57,459 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,800 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $1,313 | $1,600 |
$1,313
14,654
kWh
|
- | - | - | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $723 | $1,500 |
$544
6,155
kWh
|
$179
-
kW-mo/yr
|
- | - | |
| 03 | 2.2511: Insulate bare equipment | $3,454 | $3,900 |
$3,454
38,394
kWh
|
- | - | - | |
| 04 | 2.7233: Use properly designed and sized hvac equipment | $9,653 | - |
$9,653
107,268
kWh
|
- | - | - | |
| 05 | 2.2511: Insulate bare equipment | $1,927 | $2,160 |
$1,927
21,395
kWh
|
- | - | - | |
| 06 | 2.2514: Cover open tanks | $3,955 | $4,450 | - | - |
$3,955
-
MMBtu
|
- | |
| 07 | 4.632: Change operating conditions | $7,654 | $20,000 | - | - | - | $7,654 | |
| 08 | 4.424: Improve space comfort conditioning | $1,980 | $1,030 | - | - | - | $1,980 | |
| 09 | 4.611: Begin a practice of predictive / preventative maintenance | $1,800 | $120 | - | - | - | $1,800 | |
| 10 | 4.652: Replace existing equipment with more suitable substitutes | $25,000 | $800 | - | - | - | $25,000 | |
| TOTAL RECOMMENDED | $57,459 | $35,560 |
$16,891
187,866
kWh
|
$179
-
kW-mo/yr
|
$3,955
-
MMBtu
|
$36,434 | ||
| TOTAL IMPLEMENTED | $1,800 | $120 | - | - | - | $1,800 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs