ITAC Assessment: HO0187
ITAC logo
ITAC Assessment: HO0187
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Narrow Fabrics
NAICS
n/a
SIC 2396: Automotive Trimmings, Apparel Findings, and Related Products
Sales Range $5
M
to 10
M
# of Employees 100
Plant Area 98,000
ft2
Annual Production 90,000
thousand feet
Production Hrs. Annual 2,250
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $29,628 470,399
kWh
Electricity Demand $48,284 2,157
kW-mo/yr
Electricity Fees $4,243 -
Natural Gas $8,068 1,000
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,969 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,199

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $26,545 $90,112 $9,588
152,403
kWh
$16,957
-
kW-mo/yr
- - -
02 2.4133: Use most efficient type of electric motors $133 $415 $133
2,052
kWh
- - - -
03 2.4221: Install compressor air intakes in coolest locations $267 $500 $99
1,465
kWh
$168
-
kW-mo/yr
- - -
04 2.2511: Insulate bare equipment $1,092 $650 - - $1,092
-
MMBtu
- -
05 2.8114: Change rate schedules or other changes in utility service $807 $250 - - - - $807
06 3.5217: Reuse / recycle/ sell paper products $1,125 $100 - - - $1,125
-
lb
-
TOTAL RECOMMENDED $29,969 $92,027 $9,820
155,920
kWh
$17,125
-
kW-mo/yr
$1,092
-
MMBtu
$1,125
-
lb
$807
TOTAL IMPLEMENTED $2,199 $850 $99
1,465
kWh
$168
-
kW-mo/yr
- $1,125
-
lb
$807
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs