ITAC Assessment: DS0070
ITAC logo
ITAC Assessment: DS0070
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Photographic Printers
NAICS
n/a
SIC 3861: Photographic Equipment and Supplies
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 62,000
ft2
Annual Production 100
pieces
Production Hrs. Annual 2,600
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $27,850 898,593
kWh
Electricity Demand $20,790 2,688
kW-mo/yr
Electricity Fees $2,649 -
Natural Gas $7,072 1,656
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,410 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,865

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 3.5315: Lease / purchase baler; sell cardboard to recycler $3,276 $4,750 - - - $3,276
-
lb
02 2.7142: Utilize higher efficiency lamps and/or ballasts $5,725 $11,774 $3,017
97,304
kWh
$2,708
-
kW-mo/yr
- -
03 3.5311: Recover and reuse waste material $544 - - - - $544
-
lb
04 2.6218: Turn off equipment when not in use $181 - $181
5,862
kWh
- - -
05 2.7261: Install timers and/or thermostats $1,684 $2,310 - - $1,684
-
MMBtu
-
TOTAL RECOMMENDED $11,410 $18,834 $3,198
103,166
kWh
$2,708
-
kW-mo/yr
$1,684
-
MMBtu
$3,820
-
lb
TOTAL IMPLEMENTED $1,865 $2,310 $181
5,862
kWh
- $1,684
-
MMBtu
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs