Assessment Year | 1999 |
---|---|
Principal Product | compressed air system components |
NAICS |
n/a
|
SIC | 3596: Scales and Balances, Except Laboratory |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
195,059
ft2
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $108,693 | 5,930,832 |
kWh
|
$0.018 |
Electricity Demand | $187,684 | 13,427 |
kW-mo/yr
|
$13.98 |
Electricity Fees | $204 | - |
|
- |
Natural Gas | $63,630 | 19,692 |
MMBtu
|
$3.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,670 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,110 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,280 | $1,000 |
$1,410
77,374
kWh
|
$2,910
-
kW-mo/yr
|
- | - | $(-1,040.0) | - | - | |
02 | 2.6218: Turn off equipment when not in use | $3,560 | $450 |
$660
36,342
kWh
|
$2,900
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $600 | - |
$620
34,291
kWh
|
$1,350
-
kW-mo/yr
|
- | - | - | $(-1,370.0) | - | |
04 | 3.4114: Replace city water with recycled water via cooling tower | $19,000 | $21,600 |
$(-790.0)
(-43,376)
kWh
|
$(-1,150.0)
-
kW-mo/yr
|
$9,900
-
Tgal
|
- | - | - |
$11,040
-
Tgal
|
|
05 | 3.6192: Use a less expensive method of waste removal | $230 | - | - | - | - |
$250
-
lb
|
- | $(-20.0) | - | |
TOTAL RECOMMENDED | $26,670 | $23,050 |
$1,900
104,631
kWh
|
$6,010
-
kW-mo/yr
|
$9,900
-
Tgal
|
$250
-
lb
|
$(-1,040.0) | $(-1,390.0) |
$11,040
-
Tgal
|
||
TOTAL IMPLEMENTED | $4,110 | $1,000 |
$2,030
111,665
kWh
|
$4,260
-
kW-mo/yr
|
- |
$250
-
lb
|
$(-1,040.0) | $(-1,390.0) | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs