ITAC Assessment: HO0178
ITAC logo
ITAC Assessment: HO0178
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Manufacturing contracts
NAICS
n/a
SIC 3823: Industrial Instruments for Measurement, Display, and Control of Process Variables; and Related Products
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 85,000
ft2
Annual Production 30
pieces
Production Hrs. Annual 8,400
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $285,792 3,875,440
kWh
Electricity Demand $54,633 8,437
kW-mo/yr
Electricity Fees $11,616 -
Natural Gas $85,026 22,164
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $75,729 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $46,238

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,430 $2,149 $1,275
16,706
kWh
$155
-
kW-mo/yr
- - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,308 $4,853 $2,940
39,859
kWh
$368
-
kW-mo/yr
- - - - -
03 2.7111: Reduce illumination to minimum necessary levels $1,828 $300 $1,595
21,981
kWh
$233
-
kW-mo/yr
- - - - -
04 2.7135: Install occupancy sensors $244 $200 $244
3,224
kWh
- - - - - -
05 2.2414: Use waste heat from hot flue gases to preheat $2,066 $1,476 - - - $2,066
-
MMBtu
- - -
06 2.4221: Install compressor air intakes in coolest locations $2,272 $1,000 $2,028
27,550
kWh
$244
-
kW-mo/yr
- - - - -
07 2.2511: Insulate bare equipment $282 $200 - - - $282
-
MMBtu
- - -
08 3.1191: Change procedures / equipment / operating conditions $828 - - - - - $828
-
gal
- -
09 2.3511: Use plant owned transformers or lease transformers $22,864 $27,500 - - $22,864 - - - -
10 3.1191: Change procedures / equipment / operating conditions $2,500 $360 - - - - - $2,500
-
lb
-
11 3.1191: Change procedures / equipment / operating conditions $20,000 $2,000 - - - - - $20,000
-
lb
-
12 4.611: Begin a practice of predictive / preventative maintenance $11,429 $30,000 - - - - - - $11,429
13 2.8112: Combine utility meters $2,733 $3,000 - $2,733
-
kW-mo/yr
- - - - -
14 3.7193: Use high pressure wash systems $3,945 $500 - - - - - - $3,945
TOTAL RECOMMENDED $75,729 $73,538 $8,082
109,320
kWh
$3,733
-
kW-mo/yr
$22,864 $2,348
-
MMBtu
$828
-
gal
$22,500
-
lb
$15,374
TOTAL IMPLEMENTED $46,238 $41,262 $6,487
87,339
kWh
$767
-
kW-mo/yr
- $282
-
MMBtu
$828
-
gal
$22,500
-
lb
$15,374
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs