| Assessment Year | 1998 |
|---|---|
| Principal Product | Manufacturing contracts |
| NAICS |
n/a
|
| SIC | 3823: Industrial Instruments for Measurement, Display, and Control of Process Variables; and Related Products |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
85,000
ft2
|
| Annual Production | 30
pieces
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $285,792 | 3,875,440 |
kWh
|
$0.074 |
| Electricity Demand | $54,633 | 8,437 |
kW-mo/yr
|
$6.48 |
| Electricity Fees | $11,616 | - |
|
- |
| Natural Gas | $85,026 | 22,164 |
MMBtu
|
$3.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $75,729 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $46,238 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,430 | $2,149 |
$1,275
16,706
kWh
|
$155
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,308 | $4,853 |
$2,940
39,859
kWh
|
$368
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $1,828 | $300 |
$1,595
21,981
kWh
|
$233
-
kW-mo/yr
|
- | - | - | - | - | |
| 04 | 2.7135: Install occupancy sensors | $244 | $200 |
$244
3,224
kWh
|
- | - | - | - | - | - | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $2,066 | $1,476 | - | - | - |
$2,066
-
MMBtu
|
- | - | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $2,272 | $1,000 |
$2,028
27,550
kWh
|
$244
-
kW-mo/yr
|
- | - | - | - | - | |
| 07 | 2.2511: Insulate bare equipment | $282 | $200 | - | - | - |
$282
-
MMBtu
|
- | - | - | |
| 08 | 3.1191: Change procedures / equipment / operating conditions | $828 | - | - | - | - | - |
$828
-
gal
|
- | - | |
| 09 | 2.3511: Use plant owned transformers or lease transformers | $22,864 | $27,500 | - | - | $22,864 | - | - | - | - | |
| 10 | 3.1191: Change procedures / equipment / operating conditions | $2,500 | $360 | - | - | - | - | - |
$2,500
-
lb
|
- | |
| 11 | 3.1191: Change procedures / equipment / operating conditions | $20,000 | $2,000 | - | - | - | - | - |
$20,000
-
lb
|
- | |
| 12 | 4.611: Begin a practice of predictive / preventative maintenance | $11,429 | $30,000 | - | - | - | - | - | - | $11,429 | |
| 13 | 2.8112: Combine utility meters | $2,733 | $3,000 | - |
$2,733
-
kW-mo/yr
|
- | - | - | - | - | |
| 14 | 3.7193: Use high pressure wash systems | $3,945 | $500 | - | - | - | - | - | - | $3,945 | |
| TOTAL RECOMMENDED | $75,729 | $73,538 |
$8,082
109,320
kWh
|
$3,733
-
kW-mo/yr
|
$22,864 |
$2,348
-
MMBtu
|
$828
-
gal
|
$22,500
-
lb
|
$15,374 | ||
| TOTAL IMPLEMENTED | $46,238 | $41,262 |
$6,487
87,339
kWh
|
$767
-
kW-mo/yr
|
- |
$282
-
MMBtu
|
$828
-
gal
|
$22,500
-
lb
|
$15,374 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs