Assessment Year | 1998 |
---|---|
Principal Product | iron castings |
NAICS |
n/a
|
SIC | 3322: Malleable Iron Foundries |
Sales Range | $10 M to 50M |
# of Employees | 314 |
Plant Area |
140,000
ft2
|
Annual Production | 7,600
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $211,039 | 5,109,906 |
kWh
|
$0.041 |
Electricity Demand | $91,557 | 14,217 |
kW-mo/yr
|
$6.44 |
Electricity Fees | $66,797 | - |
|
- |
Natural Gas | $346,224 | 54,345 |
MMBtu
|
$6.37 |
Coal | $723,840 | 170,478 |
MMBtu
|
$4.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $55,112 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,116 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,898 | $20,287 |
$3,739
89,977
kWh
|
$1,159
-
kW-mo/yr
|
- | - | |
02 | 2.4133: Use most efficient type of electric motors | $875 | $2,308 |
$875
21,102
kWh
|
- | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,918 | $1,500 |
$1,476
35,756
kWh
|
$442
-
kW-mo/yr
|
- | - | |
04 | 2.2511: Insulate bare equipment | $4,561 | $7,680 | - | - |
$4,561
-
MMBtu
|
- | |
05 | 4.513: Re-arrange equipment layout to reduce labor costs | $7,800 | $8,000 | - | - | - | $7,800 | |
06 | 4.514: Re-arrange equipment layout to reduce handling costs | $24,960 | $5,000 | - | - | - | $24,960 | |
07 | 4.431: Train operators for maximum operating efficiency | $7,800 | - | - | - | - | $7,800 | |
08 | 4.652: Replace existing equipment with more suitable substitutes | $2,300 | - | - | - | - | $2,300 | |
TOTAL RECOMMENDED | $55,112 | $44,775 |
$6,090
146,835
kWh
|
$1,601
-
kW-mo/yr
|
$4,561
-
MMBtu
|
$42,860 | ||
TOTAL IMPLEMENTED | $9,116 | $21,787 |
$5,215
125,733
kWh
|
$1,601
-
kW-mo/yr
|
- | $2,300 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs