| Assessment Year | 1998 |
|---|---|
| Principal Product | Loose leaf Binders |
| NAICS |
n/a
|
| SIC | 2782: Blankbooks, Looseleaf Binders and Devices |
| Sales Range | $1 M to 5M |
| # of Employees | 36 |
| Plant Area |
50,000
ft2
|
| Annual Production | 1,030,000
pieces
|
| Production Hrs. Annual | 2,250
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $24,812 | 308,030 |
kWh
|
$0.081 |
| Electricity Demand | $19,651 | 1,562 |
kW-mo/yr
|
$12.58 |
| Electricity Fees | $(-581.0) | - |
|
- |
| Natural Gas | $17,897 | 2,668 |
MMBtu
|
$6.71 |
| Fuel Oil #2 | $7,815 | 1,075 |
MMBtu
|
$7.27 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,377 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,262 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,879 | $13,312 |
$1,521
18,757
kWh
|
$1,358
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $575 | $20 |
$297
3,810
kWh
|
$278
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,492 | $300 |
$1,803
22,274
kWh
|
$1,689
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $708 | $990 | - | - |
$708
-
MMBtu
|
- | - | |
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $316 | $47 | - | - |
$316
-
MMBtu
|
- | - | |
| 06 | 4.652: Replace existing equipment with more suitable substitutes | $3,907 | $1,500 | - | - | - |
$3,907
-
MMBtu
|
- | |
| 07 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $500 | $2,000 | - | - | - | - | $500 | |
| TOTAL RECOMMENDED | $12,377 | $18,169 |
$3,621
44,841
kWh
|
$3,325
-
kW-mo/yr
|
$1,024
-
MMBtu
|
$3,907
-
MMBtu
|
$500 | ||
| TOTAL IMPLEMENTED | $7,262 | $13,679 |
$3,621
44,841
kWh
|
$3,325
-
kW-mo/yr
|
$316
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs