ITAC Assessment: HO0155
ITAC logo
ITAC Assessment: HO0155
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Pizza
NAICS
n/a
SIC 2038: Frozen Specialties, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 110
Plant Area 150,000
ft2
Annual Production 6,000,000
units
Production Hrs. Annual 6,700
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $577,319 7,422,040
kWh
Electricity Demand $165,661 18,795
kW-mo/yr
Electricity Fees $(-151,000.0) -
Natural Gas $123,345 28,776
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $72,787 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,268

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Water Consumption Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,138 $9,401 $4,195
53,927
kWh
$943
-
kW-mo/yr
- - - - -
02 2.4133: Use most efficient type of electric motors $1,489 $1,607 $1,489
19,050
kWh
- - - - - -
03 2.4221: Install compressor air intakes in coolest locations $2,556 $1,000 $2,125
27,257
kWh
$431
-
kW-mo/yr
- - - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,298 $15,334 $4,298
36,342
kWh
- - - - - -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,141 $2,400 $948
12,309
kWh
$193
-
kW-mo/yr
- - - - -
06 2.7496: Install partitions to reduce size of conditioned space $1,462 $6,000 $1,220
15,826
kWh
$242
-
kW-mo/yr
- - - - -
07 2.2414: Use waste heat from hot flue gases to preheat $2,263 $1,363 - - $2,263
-
MMBtu
- - - -
08 4.441: Install automatic packing equipment $5,460 $25,000 - - - - $5,460 - -
09 3.7193: Use high pressure wash systems $33,480 $1,000 - - - - $27,000 - $6,480
-
Tgal
10 3.1191: Change procedures / equipment / operating conditions $6,000 $500 - - - - - $6,000 -
11 3.5317: Sell / offer by-product as animal feed $9,500 $100 - - - $9,500
-
lb
- - -
TOTAL RECOMMENDED $72,787 $63,705 $14,275
164,711
kWh
$1,809
-
kW-mo/yr
$2,263
-
MMBtu
$9,500
-
lb
$32,460 $6,000 $6,480
-
Tgal
TOTAL IMPLEMENTED $27,268 $29,570 $3,614
46,307
kWh
$431
-
kW-mo/yr
$2,263
-
MMBtu
$9,500
-
lb
$5,460 $6,000 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs