Assessment Year | 1997 |
---|---|
Principal Product | Printed Cicuit Boards |
NAICS |
n/a
|
SIC | 3672: Printed Circuit Boards |
Sales Range | $1 M to 5M |
# of Employees | 51 |
Plant Area |
10,000
ft2
|
Annual Production | 250,000
pieces
|
Production Hrs. Annual | 5,096
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $60,405 | 668,816 |
kWh
|
$0.090 |
Electricity Demand | $21,404 | 2,523 |
kW-mo/yr
|
$8.48 |
Electricity Fees | $14,372 | - |
|
- |
Natural Gas | $2,109 | 231 |
MMBtu
|
$9.13 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $52,397 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,638 | $5,469 |
$2,991
33,118
kWh
|
$647
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $241 | $245 |
$241
2,638
kWh
|
- | - | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $482 | $400 |
$397
4,396
kWh
|
$85
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $2,241 | $6,000 |
$1,985
21,981
kWh
|
$256
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,832 | $10,000 |
$1,605
17,878
kWh
|
$1,780
-
kW-mo/yr
|
$(-553.0)
-
MMBtu
|
- | - | - | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $6,500 | $6,500 | - | - | - | - |
$6,500
-
lb
|
- | |
07 | 3.7141: Improve cleaning efficiency by maintaining cleaning system | $32,500 | $6,000 | - | - | - | - |
$52,500
-
lb
|
$(-20,000.0)
-
Tgal
|
|
08 | 3.3131: Use evaporation to concentrate material | $3,963 | $1,500 | - | - |
$(-237.0)
-
MMBtu
|
$4,200
-
gal
|
- | - | |
TOTAL RECOMMENDED | $52,397 | $36,114 |
$7,219
80,011
kWh
|
$2,768
-
kW-mo/yr
|
$(-790.0)
-
MMBtu
|
$4,200
-
gal
|
$59,000
-
lb
|
$(-20,000.0)
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs