Assessment Year | 1997 |
---|---|
Principal Product | Powder coating |
NAICS |
n/a
|
SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 15 |
Plant Area |
15,000
ft2
|
Annual Production | 50,000
lb
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $17,471 | 178,781 |
kWh
|
$0.098 |
Electricity Demand | $8,887 | 800 |
kW-mo/yr
|
$11.11 |
Electricity Fees | $1,862 | - |
|
- |
Natural Gas | $63,328 | 7,790 |
MMBtu
|
$8.13 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $192,841 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $175,203 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $238 | $234 |
$238
2,345
kWh
|
- | - | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $616 | $500 |
$318
2,638
kWh
|
$298
-
kW-mo/yr
|
- | - | - | - | |
03 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $2,400 | $6,500 | - | - | - |
$2,400
-
lb
|
- | - | |
04 | 2.2511: Insulate bare equipment | $16,827 | $7,700 | - | - |
$16,827
-
MMBtu
|
- | - | - | |
05 | 4.513: Re-arrange equipment layout to reduce labor costs | $15,000 | $200 | - | - | - | - | $15,000 | - | |
06 | 4.321: Optimize production lot sizes and inventories | $104,000 | - | - | - | - | - | $104,000 | - | |
07 | 3.5311: Recover and reuse waste material | $53,760 | - | - | - | - | - | $48,000 | $5,760 | |
TOTAL RECOMMENDED | $192,841 | $15,134 |
$556
4,983
kWh
|
$298
-
kW-mo/yr
|
$16,827
-
MMBtu
|
$2,400
-
lb
|
$167,000 | $5,760 | ||
TOTAL IMPLEMENTED | $175,203 | $8,200 |
$318
2,638
kWh
|
$298
-
kW-mo/yr
|
$16,827
-
MMBtu
|
- | $152,000 | $5,760 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs