Assessment Year | 1996 |
---|---|
Principal Product | Cosmetics |
NAICS |
n/a
|
SIC | 2844: Perfumes, Cosmetics, and Other Toilet Preparations |
Sales Range | $100 M to 500M |
# of Employees | 350 |
Plant Area |
205,000
ft2
|
Annual Production | 120,000,000
pieces
|
Production Hrs. Annual | 6,400
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $742,725 | 9,453,986 |
kWh
|
$0.079 |
Electricity Demand | $201,909 | 22,643 |
kW-mo/yr
|
$8.92 |
Electricity Fees | $(-164,312.0) | - |
|
- |
Natural Gas | $115,488 | 30,897 |
MMBtu
|
$3.74 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,923 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,523 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $3,210 | $1,200 |
$2,650
33,705
kWh
|
$560
-
kW-mo/yr
|
- | - | |
02 | 2.4133: Use most efficient type of electric motors | $5,138 | $9,130 |
$4,239
53,927
kWh
|
$899
-
kW-mo/yr
|
- | - | |
03 | 2.2135: Repair and eliminate steam leaks | $175 | $100 | - | - |
$175
-
MMBtu
|
- | |
04 | 3.4114: Replace city water with recycled water via cooling tower | $1,400 | $5,000 | - | - | - |
$1,400
-
Tgal
|
|
TOTAL RECOMMENDED | $9,923 | $15,430 |
$6,889
87,632
kWh
|
$1,459
-
kW-mo/yr
|
$175
-
MMBtu
|
$1,400
-
Tgal
|
||
TOTAL IMPLEMENTED | $8,523 | $10,430 |
$6,889
87,632
kWh
|
$1,459
-
kW-mo/yr
|
$175
-
MMBtu
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs