Assessment Year | 1995 |
---|---|
Principal Product | Candles |
NAICS |
n/a
|
SIC | 3999: Manufacturing Industries, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
35,500
ft2
|
Annual Production | 4,000,000
lb
|
Production Hrs. Annual | 1,940
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $24,962 | 118,406 |
kWh
|
$0.21 |
Natural Gas | $22,651 | 3,382 |
MMBtu
|
$6.70 |
Fuel Oil #2 | $15,235 | 2,179 |
MMBtu
|
$6.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $5,830 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $400 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,234 | $761 |
$1,234
5,862
kWh
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $247 | $374 |
$247
1,172
kWh
|
- | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $151 | $305 |
$151
879
kWh
|
- | - | - | |
04 | 2.2136: Install / repair insulation on steam lines | $96 | $53 | - |
$56
-
MMBtu
|
$40
-
MMBtu
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $229 | $500 |
$229
1,172
kWh
|
- | - | - | |
06 | 2.1232: Keep boiler tubes clean | $2,908 | $3,000 | - |
$1,697
-
MMBtu
|
$1,211
-
MMBtu
|
- | |
07 | 2.8112: Combine utility meters | $400 | - | - | - | - | $400 | |
08 | 2.8121: Apply for tax-free status for energy purchases | $565 | - | - | - | - | $565 | |
TOTAL RECOMMENDED | $5,830 | $4,993 |
$1,861
9,085
kWh
|
$1,753
-
MMBtu
|
$1,251
-
MMBtu
|
$965 | ||
TOTAL IMPLEMENTED | $400 | - | - | - | - | $400 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs