ITAC Assessment: HO0096
ITAC logo
ITAC Assessment: HO0096
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Assembly & Test Systems
NAICS
n/a
SIC 3549: Metalworking Machinery, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 175
Plant Area 78,000
ft2
Annual Production 40
pieces
Production Hrs. Annual 3,952
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $254,978 2,210,434
kWh
Natural Gas $34,727 4,425
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,534 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,913

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $12,527 $13,916 $12,527
109,027
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,442 $6,685 $4,442
38,687
kWh
-
03 2.4133: Use most efficient type of electric motors $101 $417 $101
879
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $1,178 $900 $1,178
10,258
kWh
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $2,471 $1,000 - $2,471
-
MMBtu
06 2.7135: Install occupancy sensors $695 $400 $695
6,155
kWh
-
07 2.2136: Install / repair insulation on steam lines $120 $141 - $120
-
MMBtu
TOTAL RECOMMENDED $21,534 $23,459 $18,943
165,006
kWh
$2,591
-
MMBtu
TOTAL IMPLEMENTED $6,913 $7,685 $4,442
38,687
kWh
$2,471
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs