ITAC Assessment: HO0075
ITAC logo
ITAC Assessment: HO0075
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Aluminum Die Casting
NAICS
n/a
SIC 3363: Aluminum Die-Castings
Sales Range $1
M
to 5
M
# of Employees 25
Plant Area 19,000
ft2
Annual Production 628,000
lb
Production Hrs. Annual 2,340
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $83,978 822,098
kWh
Natural Gas $46,586 10,082
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,858 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,858

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,404 $2,245 $1,404
13,775
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $75 $205 $75
879
kWh
-
03 2.7124: Make a practice of turning off lights when not needed $630 - $630
6,155
kWh
-
04 2.4133: Use most efficient type of electric motors $400 $1,132 $400
3,810
kWh
-
05 2.4221: Install compressor air intakes in coolest locations $361 $200 $361
3,517
kWh
-
06 2.8113: Purchase gas directly from a contract gas supplier $6,988 $2,000 - $6,988
TOTAL RECOMMENDED $9,858 $5,782 $2,870
28,136
kWh
$6,988
TOTAL IMPLEMENTED $9,858 $5,782 $2,870
28,136
kWh
$6,988
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs