ITAC Assessment: HO0067
ITAC logo
ITAC Assessment: HO0067
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Bottles
NAICS
n/a
SIC 2834: Pharmaceutical Preparations
Sales Range $50
M
to 100
M
# of Employees 150
Plant Area 30,000
ft2
Annual Production 5,000,000
pieces
Production Hrs. Annual 4,160
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $193,300 2,187,866
kWh
Natural Gas $21,132 3,432
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,922 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,665 $2,873 $2,665
30,188
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,033 $3,266 $1,033
11,723
kWh
-
03 2.4133: Use most efficient type of electric motors $193 $497 $193
2,052
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $824 $900 $824
9,379
kWh
-
05 2.2136: Install / repair insulation on steam lines $135 $135 - $135
-
MMBtu
06 2.6218: Turn off equipment when not in use $72 - $72
879
kWh
-
TOTAL RECOMMENDED $4,922 $7,671 $4,787
54,221
kWh
$135
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs