ITAC Assessment: HO0062
ITAC logo
ITAC Assessment: HO0062
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Plastic Molded Products
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 25
Plant Area 42,000
ft2
Annual Production 500
ton
Production Hrs. Annual 6,240
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $41,108 340,563
kWh
Natural Gas $50,848 8,978
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,320 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,603 $1,940 $3,603
29,894
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,481 $1,923 $1,481
12,309
kWh
03 2.4133: Use most efficient type of electric motors $199 $204 $199
1,758
kWh
04 2.4221: Install compressor air intakes in coolest locations $870 $1,000 $870
7,327
kWh
05 2.2511: Insulate bare equipment $167 $96 $167
8,792
kWh
TOTAL RECOMMENDED $6,320 $5,163 $6,320
60,080
kWh
TOTAL IMPLEMENTED - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs