ITAC Assessment: HO0049
ITAC logo
ITAC Assessment: HO0049
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Printed Corrugated Boxes
NAICS
n/a
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 100,000
ft2
Annual Production 24,000
ton
Production Hrs. Annual 4,160
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $331,756 3,042,204
kWh
Fuel Oil #6 $109,221 33,625
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,182 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,802

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #6 Savings Other Energy Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,007 $3,704 $4,007
36,928
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $841 $1,654 $841
7,620
kWh
- -
03 2.4133: Use most efficient type of electric motors $1,694 $3,792 $1,694
15,533
kWh
- -
04 2.4221: Install compressor air intakes in coolest locations $5,537 $2,000 $5,537
50,703
kWh
- -
05 2.2511: Insulate bare equipment $149 $224 - $149
-
MMBtu
-
06 2.3212: Optimize plant power factor $12,954 $9,630 - - $12,954
-
MMBtu
TOTAL RECOMMENDED $25,182 $21,004 $12,079
110,784
kWh
$149
-
MMBtu
$12,954
-
MMBtu
TOTAL IMPLEMENTED $17,802 $14,988 $4,848
44,548
kWh
- $12,954
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #6 Savings Other Energy Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs