Assessment Year | 1991 |
---|---|
Principal Product | BOLTS AND SCREWS |
NAICS |
n/a
|
SIC | 3452: Bolts, Nuts, Screws, Rivets, and Washers |
Sales Range | $1 M to 5M |
# of Employees | 35 |
Plant Area |
n/a
|
Annual Production | 7,000,000
lb
|
Production Hrs. Annual | 2,825
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $165,221 | 1,165,885 |
kWh
|
$0.14 |
Natural Gas | $5,994 | 1,030 |
MMBtu
|
$5.82 |
Fuel Oil #2 | $15,600 | 1,820 |
MMBtu
|
$8.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,396 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,070 | $1,021 |
$2,290
21,102
kWh
|
- | $(-220.0) | |
02 | 2.4133: Use most efficient type of electric motors | $1,063 | $667 |
$1,063
7,620
kWh
|
- | - | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $904 | $800 | - |
$1,404
-
MMBtu
|
$(-500.0) | |
04 | 2.6212: Turn off equipment during breaks, reduce operating time | $2,695 | - |
$2,695
19,050
kWh
|
- | - | |
05 | 2.2135: Repair and eliminate steam leaks | $714 | $50 | - |
$714
-
MMBtu
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $2,950 | $1,000 |
$2,950
20,809
kWh
|
- | - | |
TOTAL RECOMMENDED | $10,396 | $3,538 |
$8,998
68,581
kWh
|
$2,118
-
MMBtu
|
$(-720.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs