ITAC Assessment: HO0004
ITAC logo
ITAC Assessment: HO0004
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product BOLTS AND SCREWS
NAICS
n/a
SIC 3452: Bolts, Nuts, Screws, Rivets, and Washers
Sales Range $1
M
to 5
M
# of Employees 35
Plant Area
n/a
Annual Production 7,000,000
lb
Production Hrs. Annual 2,825
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $165,221 1,165,885
kWh
Natural Gas $5,994 1,030
MMBtu
Fuel Oil #2 $15,600 1,820
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,396 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #2 Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,070 $1,021 $2,290
21,102
kWh
- $(-220.0)
02 2.4133: Use most efficient type of electric motors $1,063 $667 $1,063
7,620
kWh
- -
03 2.1233: Analyze flue gas for proper air/fuel ratio $904 $800 - $1,404
-
MMBtu
$(-500.0)
04 2.6212: Turn off equipment during breaks, reduce operating time $2,695 - $2,695
19,050
kWh
- -
05 2.2135: Repair and eliminate steam leaks $714 $50 - $714
-
MMBtu
-
06 2.4221: Install compressor air intakes in coolest locations $2,950 $1,000 $2,950
20,809
kWh
- -
TOTAL RECOMMENDED $10,396 $3,538 $8,998
68,581
kWh
$2,118
-
MMBtu
$(-720.0)
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #2 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs