Assessment Year | 2002 |
---|---|
Principal Product | Specialty bolts, track spikes for railroads |
NAICS |
n/a
|
SIC | 3452: Bolts, Nuts, Screws, Rivets, and Washers |
Sales Range | $5 M to 10M |
# of Employees | 90 |
Plant Area |
48,750
ft2
|
Annual Production | 10,000,000
lb
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $118,540 | 2,416,050 |
kWh
|
$0.049 |
Electricity Demand | $84,183 | 9,803 |
kW-mo/yr
|
$8.59 |
Natural Gas | $130,798 | 35,466 |
MMBtu
|
$3.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $159,210 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $40,640 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,450 | $90 |
$3,260
66,600
kWh
|
$1,550
-
kW-mo/yr
|
- | $(-360.0) | - | |
02 | 2.3191: Use demand controller or load shedder | $4,230 | $7,000 | - |
$4,230
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,570 | $23,500 |
$2,460
50,300
kWh
|
$1,110
-
kW-mo/yr
|
- | - | - | |
04 | 3.3122: Use filtration, centrifuging to remove contaminants | $31,960 | $1,620 | - | - |
$3,330
-
gal
|
- | $28,630 | |
05 | 4.112: Replace old machine with new automatic multi-station tool | $115,000 | $100,000 | - | - | - | $120,000 | $(-5,000.0) | |
TOTAL RECOMMENDED | $159,210 | $132,210 |
$5,720
116,900
kWh
|
$6,890
-
kW-mo/yr
|
$3,330
-
gal
|
$119,640 | $23,630 | ||
TOTAL IMPLEMENTED | $40,640 | $8,710 |
$3,260
66,600
kWh
|
$5,780
-
kW-mo/yr
|
$3,330
-
gal
|
$(-360.0) | $28,630 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs