ITAC Assessment: GT0909
ITAC logo
ITAC Assessment: GT0909
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Flexible packaging
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 100,000
ft2
Annual Production 5,041,183
lb
Production Hrs. Annual 8,570
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $635,613 7,310,052
kWh
Natural Gas $4,806 486
MMBtu
Waste Disposal Costs
Water Usage $9,462 958,138
Tgal
TOTAL YEARLY COSTS $649,880
RECOMMENDED SAVINGS* $109,601 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $99,093

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Primary Product Savings
01 2.4224: Upgrade controls on compressors $3,363 $240 $3,363
38,659
kWh
-
02 2.4221: Install compressor air intakes in coolest locations $1,594 $411 $1,594
18,323
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $49,255 $36,180 $49,255
566,149
kWh
-
04 2.7425: Clean or color roof to reduce solar load $5,551 $7,915 $5,551
63,807
kWh
-
05 4.111: Add equipment/ operators to reduce production bottleneck $49,838 $321,120 $(-4,210.0)
(-48,385)
kWh
$54,048
TOTAL RECOMMENDED $109,601 $365,866 $55,553
638,553
kWh
$54,048
TOTAL IMPLEMENTED $99,093 $357,300 $45,045
517,764
kWh
$54,048
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs