| Assessment Year | 2012 |
|---|---|
| Principal Product | FiberCement Boards-Siding |
| NAICS | 327390: Other Concrete Product Manufacturing |
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $50 M to 100M |
| # of Employees | 159 |
| Plant Area |
294,500
ft2
|
| Annual Production | 26,604
thousand feet
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,051,708 | 15,057,818 |
kWh
|
$0.070 |
| Electricity Demand | $63,236 | 38,209 |
kW-mo/yr
|
$1.66 |
| Natural Gas | $550,658 | 100,120 |
MMBtu
|
$5.50 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $114,506 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $39,839 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4314: Use synthetic lubricant | $14,552 | - |
$14,552
287,013
kWh
|
- | - | - | |
| 02 | 2.6218: Turn off equipment when not in use | $304 | - |
$304
6,002
kWh
|
- | - | - | |
| 03 | 2.2136: Install / repair insulation on steam lines | $610 | $225 | - | - |
$610
-
MMBtu
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $625 | $25,217 |
$364
6,386
kWh
|
$261
-
kW-mo/yr
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $47,301 | $12,500 |
$30,785
607,199
kWh
|
$16,516
-
kW-mo/yr
|
- | - | |
| 06 | 2.2437: Recover waste heat from equipment | $34,362 | $25,440 | - | - |
$34,362
-
MMBtu
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,852 | $88,000 |
$2,826
49,572
kWh
|
$2,026
-
kW-mo/yr
|
- | - | |
| 08 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $3,990 | $12,300 | - | - |
$3,990
-
MMBtu
|
- | |
| 09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,190 | $12,795 |
$1,858
32,601
kWh
|
$1,332
-
kW-mo/yr
|
- | - | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,720 | $20,395 |
$2,118
37,162
kWh
|
$1,518
-
kW-mo/yr
|
- | $1,084 | |
| TOTAL RECOMMENDED | $114,506 | $196,872 |
$52,807
1,025,935
kWh
|
$21,653
-
kW-mo/yr
|
$38,962
-
MMBtu
|
$1,084 | ||
| TOTAL IMPLEMENTED | $39,839 | $138,657 |
$3,190
55,958
kWh
|
$2,287
-
kW-mo/yr
|
$34,362
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs