Assessment Year | 2011 |
---|---|
Principal Product | Sausages |
NAICS | 311612: Meat Processed from Carcasses |
SIC | 2013: Sausages and Other Prepared Meat Products |
Sales Range | $100 M to 500M |
# of Employees | 230 |
Plant Area |
97,000
ft2
|
Annual Production | 1,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $516,706 | 8,626,146 |
kWh
|
$0.060 |
Electricity Demand | $305,003 | 19,489 |
kW-mo/yr
|
$15.65 |
Electricity Fees | $19,791 | - |
|
- |
Natural Gas | $229,015 | 37,978 |
MMBtu
|
$6.03 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $208,568 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $149,800 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,831 | $1,250 |
$2,353
39,287
kWh
|
$1,478
-
kW-mo/yr
|
- | |
02 | 2.4314: Use synthetic lubricant | $13,152 | - |
$9,537
159,210
kWh
|
$3,615
-
kW-mo/yr
|
- | |
03 | 2.2136: Install / repair insulation on steam lines | $1,390 | $244 | - | - |
$1,390
-
MMBtu
|
|
04 | 2.2621: Modify refrigeration system to operate at a lower pressure | $75,872 | $100,115 |
$66,482
1,109,891
kWh
|
$9,390
-
kW-mo/yr
|
- | |
05 | 2.2694: Use highest temperature for chilling or cold storage | $70,097 | $17,000 |
$45,495
759,510
kWh
|
$24,602
-
kW-mo/yr
|
- | |
06 | 2.6231: Utilize controls to operate equipment only when needed | $18,994 | $5,000 |
$13,988
233,518
kWh
|
$5,006
-
kW-mo/yr
|
- | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $25,232 | $38,000 |
$25,232
421,240
kWh
|
- | - | |
TOTAL RECOMMENDED | $208,568 | $161,609 |
$163,087
2,722,656
kWh
|
$44,091
-
kW-mo/yr
|
$1,390
-
MMBtu
|
||
TOTAL IMPLEMENTED | $149,800 | $118,365 |
$114,330
1,908,688
kWh
|
$35,470
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs