ITAC Assessment: GT0845
ITAC logo
ITAC Assessment: GT0845
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Gas Regulation Equipment
NAICS 333992: Welding and Soldering Equipment Manufacturing
SIC 3548: Electric and Gas Welding and Soldering Equipment
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 86,000
ft2
Annual Production 2,600,000
pieces
Production Hrs. Annual 6,262
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $182,663 3,886,449
kWh
Electricity Demand $137,443 8,047
kW-mo/yr
Electricity Fees $1,931 -
Natural Gas $2,731 213
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $88,269 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $32,505

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $17,571 $31,022 $10,660
225,202
kWh
$6,911
-
kW-mo/yr
- -
02 2.8112: Combine utility meters $6,697 - - - $6,697 -
03 2.4231: Reduce the pressure of compressed air to the minimum required $2,196 - $1,294
27,537
kWh
$902
-
kW-mo/yr
- -
04 2.4239: Eliminate or reduce compressed air usage $22,129 $26,550 $198
4,217
kWh
$21,931
-
kW-mo/yr
- -
05 2.7261: Install timers and/or thermostats $8,290 $4,750 $6,683
141,629
kWh
- - $1,607
-
MMBtu
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $24,215 $2,000 $14,274
303,707
kWh
$9,941
-
kW-mo/yr
- -
07 2.7313: Recycle air for heating, ventilation and air conditioning $3,956 $4,000 $3,956
84,171
kWh
- - -
08 2.7135: Install occupancy sensors $3,215 $3,600 $3,215
67,392
kWh
- - -
TOTAL RECOMMENDED $88,269 $71,922 $40,280
853,855
kWh
$39,685
-
kW-mo/yr
$6,697 $1,607
-
MMBtu
TOTAL IMPLEMENTED $32,505 $6,750 $20,957
445,336
kWh
$9,941
-
kW-mo/yr
- $1,607
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs